There are currently no alerts.

Drummond Court & Leaman Street Water Main Renewal

Sackville Trenching, on behalf of Halifax Water and Halifax Regional Municipality (HRM), will be undertaking work on Drummond Court and Leaman Street. The Halifax Water portion of this work will include the replacement of the water main and any public or private lead service lines in the area. Customers with a lead service line will be contacted directly by Halifax Water with more information.

This work will begin in June and is expected to be complete by mid-September 2021. The typical hours of work will be 7:00 AM to 7:00 PM, Monday to Friday. During this work, portions of the street will be closed as sections of water main are replaced. The contractor will communicate with residents as section closures change.

Project Map
Drummond Court & Leaman Street – Water Main Renewal Project Map
Water Service Shutdown for Temporary Water Connections

If your property is within the shaded area on the attached map, your property will be connected to temporary water.

The contractor will be connecting buildings in the project area to a temporary water system that brings water from fire hydrants in the surrounding area (that will not be impacted by this work) to each impacted property so that the water mains that normally provide those properties with water can be replaced without customers having to go without water service for the length of the project.

Water service must be temporarily turned off at each property as the contractor disconnects each property from the old water connection and onto the temporary water connection.

Starting as early as June 21, 2021, the contractor will begin laying out, sanitizing, testing and connecting the temporary water lines to the properties shown on the attached map. This work will take approximately one to two weeks to complete (weather permitting).

The contractor will make the temporary water connections at an outdoor tap (usually in the backyard) for each property (more information on the next page.) Connections will take place between 7:00 AM and 6:00 PM. Once the connection is complete, the building should have regular water service for the length of the project.

The contractor may require periodic access to the back of your property during construction to ensure the temporary water line is in working condition. These temporary water lines will be disconnected at the end of the project, and each property will be connected to the new water main.

Construction & Contractor Work During COVID-19

During this project, from time to time, you will see workers within 2 metres of each other while they work to maintain the critical water, wastewater, and stormwater infrastructure serving your home.  Halifax Water is still mindful of the recommendations to maintain a 2 metre distance between employees and contractors, and every effort will be made to achieve this. However, some tasks cannot be completed safely otherwise. As an essential service, in these instances, Halifax Water and its contractors have been exempt from the 2 metre social/physical distancing rules. Halifax Water and its contractors will use additional PPE to protect themselves when undertaking these activities.  

We ask that residents please ensure they give construction crews at least 2 metres of distancing as well.

Community Notices

Find past project updates below:

  • Community Notice 1 - June 15, 2021
Contact
Jonathan MacDonald, P.Eng
Project Manager, Halifax Water
Phone:
902-818-0913
Email:
Conrad Allison
Construction Inspector, HRM
Phone:
902-476-4722
Email:
Cameron Haley
Project Manager, Sackville Trenching
Phone:
902-802-4444
Email:
Customer Care Centre
Halifax Water
Phone:
902-420-9287
Email: